Water Sanitation and Hygiene - Kagulu - Namutumba

Visit by Alex Walyomu on 2019-04-08

Report ID
4889
Created by
Alex Walyomu
Created date
2019-04-09 12:42:18 UTC
Modified by
Alex Walyomu
Modified date
2019-04-09 13:03:09 UTC
Trip Time
10:43-17:49 (7 h 6 m)
Village Time
13:14-15:46 (2 h 32 m)
Travel Time
4 h 34 m

Water Community Meeting

Meeting Topic
land agreement 
How Many Men Attended
17 
How Many Women Attended
29 
Staff Attendees
Walyomu Alex 
Government Attendess
LC1,VHT 
Visitor Attendees
 
Total Attendance
46 
Look Up
 
Notes
Alex went to Kagulu to have a meeting with the community members and complete the land agreement where the borehole was drilled. The point where the new borehole is to be drilled is located at the border of two different land owners. It was very important to have both people to agree together and they were very happy to give out their land away at no cost to their village. A piece of 20ft by 35ft was given out by Kaida Joshua and livingston. The village men also managed to clear the anthill around the borehole. While in the meeting the community people were reminded to keep up the spirit of working together and prepare for the next team that will be carrying out pump testing and installation of the new borehole. Alex will go back to continue with the training of the water user committee and meeting with the village about the borehole ownership and responsibilities. 
Next Visit
2019-04-15 - Purpose: Training of the water user committee and emphasize on borehole contributions and responsibilities
Program Success
Program Critical Needs
Program Ownership
Other Program Observations
Program Expected Of Village
Program Staff Preparations Next Visit
 

Report Photos

6518 The water user committee chairman, Steven Kighanda and the chairman of the village signing on the land agreement
6521 The community that attended the meeting and witnessed The land owner give a piece of land measuring 20ft by 35ft
6524 The land owner mr Kaida Joswa and Living gave a piece of 20ft by 35ft
6527 The community members also were able to clear the anthill around the borehole