Water Sanitation and Hygiene - Nabituluntu - Namutumba

Visit by David Balimunsi on 2017-12-08

Report ID
496
Created by
David Balimunsi
Created date
2017-12-08 12:30:32 UTC
Modified by
Ben West
Modified date
2018-02-09 21:11:54 UTC
Trip Time
09:29-17:37 (8 h 8 m)
Village Time
12:30-15:35 (3 h 5 m)
Travel Time
5 h 3 m

Current State

Participation Rating
Success
They have taken good care of their borehole by having 250000 shillings as their borehole account money and strong fence too 
Village Critical Needs
They need fire saving Steve’s 
Village Action Steps
It is to continue working and improving on the facilities that are not meeting the reuired high good standards of hygiene and sanitation 
Staff Action Steps
It is to encourage the entire residents of the area taking good care of the borehole as well as working and reviving on the hygiene facilities that were not meeting the required sanitation standatds 
CLTS Progress
 
Sanitation Hygiene Committee
yes 
Water Users Committee
yes 
Other Class Notes
 
Community Ownership
yes 
Ownership Story
Facilities like dish racks,shower areas ,rubbish pits,houses and kitchens have been maintained and kept clean .and the borehole good status has maintained . 
Three Stone Fires
yes 
Access to Clean Water
yes 
Open Defecation
no 
Water Access Explain
 
Prevent Ownership
None 
Allow Ownership
The cooperation and mobilization between the committee members and the other residents of nabituluntu is so good. 
Village Notes
Because of the unity brought by Kibo to nabituluntu village apparently they can work together for example mr tilibagenyi the chairman Lc1 of upper nabituluntu can now lead meetings in the lower section were he used not before.For that reason Kibo staff were so happy seeing that the two villages could sit and work together in different developmental aspects,they thanked the chairman mr Samuel Galevu from the lower section and mr tulibanyi of the upper section for encouraging all the two sections coming together and working together. The borehole which Kibo repaired in the upper section was kept so good with a strong fence and even some member from the lower section were seen getting water from the upper section which never used to happen before.David asked the chairman mr tulibanyi from upper section how much-money they were having on their account for the borehole he took David to the treasures home they showed him the 220000shillings cash as their borehole account balance.kibo staff moved in fifty homes carrying out the evaluation process ,but in the different homes they were working into they kept on encouraging the residents they came across working and improving on some facilities which were not meeting the required good standards . The members were advised continuing working together in all the different village programs not forgetting having monthly borehole contributions meetings aimed at accessing the status of their borehole and the hygiene and sanitation of the different homes. They meet two V.ht,s during the process of evaluation and reminded them of their roles and responsibilities encouraging the other members about improving their sanitation standards.In general from the evaluation made by the Kibo’s staff the members have maintained their sanitation facilities according to the required standards apart from one facility the hand washing facility which was a challenge in most homes. 
Next Visit
- Purpose:
Program Success
Program Critical Needs
Program Ownership
Other Program Observations
Program Expected Of Village
Program Staff Preparations Next Visit