Water Sanitation and Hygiene - Kishaike - Namutumba

Visit by Martin Kibuuka on 2019-08-12

Report ID
6311
Created by
Martin Kibuuka
Created date
2019-08-13 08:45:25 UTC
Modified by
Martin Kibuuka
Modified date
2019-08-15 09:35:21 UTC
Trip Time
10:00-06:20 (-4 h 20 m)
Village Time
12:20-03:25 (-9 h 5 m)
Travel Time
5 h 15 m

Household visits

Which Survey
none 
Number Of Households
46 
Visits Purpose
To check on sanitation and hygiene improvement. 
Staff Attendees
Enock Madoolo,Martin Kibuuka 
Government Attendees
LC1,VHT 
Notes
Enock and Martin went to Kishaike to check on sanitation and hygiene improvement in that village. They walked around that village with the Chairman LC1 and the VHTs, encouraging those residents who are still lagging behind to improve on their sanitation facilities. Good enough the big number of homes have worked so hard on their sanitation facilities like latrine constructions, dish racks, rubbish pits, kitchens and shower facilities. For those who are still digging their new pit latrines, they promised the group that they are willing to work on them. Martin, Enock and the group was encouraging the community members about the standards, maintenance, smearing and the use of ash to eliminate flies and smell in their homes. And for those who have never worked on their dish racks, they are contributing the money for buying nails to work on them. because they have seen the value of the sanitation facilities. According to their hard working, kibo also is willing to work with them to complete their sanitation facilities. The group walked in 46homes 
Next Visit
2019-08-19 - Purpose: To check on the hand washing facilities.
Program Success
They are still continuing digging their new pit latrines.
Program Critical Needs
They need more encouragement about the latrine constructions.
Program Ownership
They are busy working on their sanitation facilities without force.
Other Program Observations
Non
Program Expected Of Village
For those who are still digging their new pit latrine, they need to construct them.
Program Staff Preparations Next Visit
To call the Chairman LC1 and tell them what is going on about those who are still working on their latrine constructions.
 

Report Photos

8345 This is how they are busy digging their new pit latrines.