Alex went back to witness the fourth day of borehole drilling in Kisiro. Because of the hard rock, it has taken the drillers more days to try reach the depth to hit more water and create enough water storage for the water got. On a very good note, they managed to get more water and estimated about 1200L/ hr of water. After four days of extensive work, the borehole was confirmed successful after the drillers yield of 1200L/ hr and very good recovery.
Next Visit
2019-11-20 - Purpose: Supervise borehole pump testing and drilling of the second hole in Kisiro
Program Success
More hope to get enough water for the well
Program Critical Needs
The hard rock makes it very hard to drill through and be able to get water
Program Ownership
Other Program Observations
Program Expected Of Village
To continue working together and give support where necessary
Program Staff Preparations Next Visit
Continue with the borehole drilling supervision
Report Photos
49.5M were drilled in the first hole
Drilling of the second water point that eventually turned out dry