Alex went back to conclude with the process of borehole drilling on the first water point making it the fourth day of drilling in this water point. The greatest challenge in this community has been the hard rock that makes it very hard to drill through. However nothing much was done on this day because the drillers ran out of fuel and had to wait for a very long time to get fuel from the head office in Kampala. Fuel eventually came late in the day and the work was pushed to the next day. 38M had been drilled so far and there was more water got at 35M.
Next Visit
2019-12-02 - Purpose: Continue with borehole drilling and supervision