Water Sanitation and Hygiene - Busene

Visit by kenethmugoda on 2021-09-20

Report ID
14040
Created by
kenethmugoda
Created date
2021-09-20 13:27:00 UTC
Modified by
kenethmugoda
Modified date
2021-09-21 07:12:05 UTC
Trip Time
09:33-17:19 (7 h 46 m)
Village Time
11:18-03:27 (-8 h 9 m)
Travel Time
15 h 37 m

Household visits

Which Survey
none 
Number Of Households
38 
Visits Purpose
Encouraging and guiding on standards of hand washi 
Staff Attendees
Steven Kambale 
Government Attendees
LC1 
Notes
Keneth and Steven went to busene to encourage and guide community members on the construction of hand washing stands. On arrival,they made visit to homes to supervise on their construction and they met a Manson person who attended the triggering session and had already constructed and promised to plaster it and build the second one in front of his compound for visitors. They also went further guiding members on the general sanitation improvement of home ideal facilities Like latrines ,racks, shower areas,as they met mr kappasi David who had no toilet before had dug the pit and raised a superstructure and awaiting for roofing of which he promised to do soon. They met mr kappasi Emmanuel who was advised to do more excavation to a recommended depth and then after slab laid over and he is positive about this . They were thankful of Kibo’s program and its works in the village as the chairman thanked keneth and Steven. 
Next Visit
2021-09-27 - Purpose: Follow up on hand washing stands and general sanitation improvement
Program Success
Yes, New latrine pits are dug and super structures raised.
Program Critical Needs
Bore hole repair
Program Ownership
Collective responsibility with building of the hand washing stands and General sanitation
Other Program Observations
Program Expected Of Village
Continue building hand washing facilities on standards and general sanitation improvement
Program Staff Preparations Next Visit
Make calls on the progress of hand washing stands construction
 

Report Photos

21381 New pit dug and with wall lining for a firm foundation
21384 New hand washing stand constructed and awaiting for plastering for durability
21387 New pit dug awaiting slab casting
21390 New latrine pit dug and superstructure raised awaiting roofing
21393 More excavation of the pit to a recommended depth and then slab cast to be laid